Plan in lanes on a Timeline
Updated
A Timeline view draws each record as a bar from its start date to its end date, in lanes. A lane is one value of a field you pick: a person, a select option such as a channel, or a linked record such as a property or a room. Records with the same value share the lane's row, so you see at a glance who or what is busy when, and where there is room.
It is the view for bookings, rotas, campaigns by channel and roadmaps by theme. For a project plan with progress and arrows for what waits on what, use a Gantt instead.
Make a timeline
- Open the views menu (the view's name at the left of the view bar).
- Under Create, choose Timeline.
- Pick the Start date and, if records last more than a day, the End date.
- Under Lanes by, pick a single select, person or link field. Choose None for one row.
- Press Create view.
The table needs a date field; without one, Timeline is greyed out. To change the fields later, use Customize timeline in the view bar.
Work on the timeline
- Day, Week, Month and Year at the top right set how much time the view shows; the arrows and Today move through it.
- Drag a bar along its lane to change its dates, or drag one of its ends to make it longer or shorter.
- Drag a bar up or down to another lane: the record's lane field changes too, in the same step, so one Undo takes both back. For a link field with several records, the record of the lane you left is swapped for the one you dropped on; the others stay.
- Double-click an empty part of a lane to add a record there, on that day and in that lane. The round + adds one too.
- Click a bar to open the record.
Good to know
- With a single select or person field, every option or person is a lane, even with nothing on it yet, so there is somewhere to drop a record. A lane for records with no value appears while there are some.
- With a link field, a record in several linked records is drawn in the lane of the first one.
- Color in the view bar colours the bars by a single select field or by conditions. Filter narrows the records, and with them the lanes that have any.
- You can move bars only when you may edit the date fields, and move them between lanes only when you may edit the lane field.
- Records without a start date are not drawn.
- An Airtable Timeline view comes over as a Timeline. Airtable's API does not say which field its swimlanes were, so pick it under Customize timeline, Lanes by.