Plan a project on a Gantt chart
Updated
A Gantt view draws each record as a bar from its start date to its end date, one row per record, with the records listed beside the bars. It is the view for project plans: you see what runs when, how far along each piece is, and what waits for what.
To see records side by side in lanes (by person, room or channel) rather than one per row, use a Timeline.
Make a Gantt chart
- Open the views menu (the view's name at the left of the view bar).
- Under Create, choose Gantt.
- Pick the Start date and the End date.
- If the table has them, pick a Progress field (a percent field) and a Depends on field.
- Press Create view.
The table needs a date field; without one, Gantt is greyed out. To change these fields later, use Customize Gantt in the view bar. Without an end date, choose None (a milestone): each record is then a milestone on its start date.
Show what depends on what
Arrows between bars come from a link field that links the table to itself, such as Depends on. Add one to the table first (see Link records), then pick it under Depends on. When a record moves later, the records that depend on it move later with it. An arrow drawn red and dashed means a record starts before the one it waits for ends.
Work on the Gantt chart
- Drag a bar to move it, or drag its end to make it longer or shorter. The record's dates change.
- Drag a bar's progress handle to set how far along it is, when the view has a progress field.
- Drag from the start or the end of a bar to another bar to link them; the link is written to the Depends on field.
- Double-click an empty part of the chart to add a record on that day. The round + adds one too.
- Click a bar, or the record's name in the list, to open the record.
- Zoom in and Zoom out move between days, weeks, months, quarters and years. The view keeps its zoom.
Good to know
- The list beside the bars shows each record's name, start, end and length in days. On a phone it shows the name only, so the bars have room.
- Color in the view bar colours the bars as it would colour rows, by a single select field or by conditions. Filter and Sort work as everywhere else.
- You can move bars only when you may edit the date fields.
- Records without a start date are not drawn.
- The Construction project, Software release plan and Work breakdown templates start with a Gantt chart, progress and dependencies filled in.